Job 05 / 6 / British Steel
Coke Oven Ammonia Still
British Steel, Scunthorpe
3inch
Ammonia still to low level pit pipework replacement
Site measureWorkshop weldedPickled and passivated
The pipework running from the coke oven ammonia still down to the low level pit had gone. KBVI stripped out the rotten carbon steel 3 inch line, site measured for its replacement, and fabricated the new pipework. Every weld was made at the KBVI workshop with the pipe fully purged, and the welds were pickled and passivated once the work was finished.
- 01Removal of the existing rotten carbon steel 3 inch pipework
- 02Site measure for the new pipework
- 03Fabrication of the new pipework on site
- 04All pipework welded at the KBVI workshop, fully purged during welding
- 05Welds pickled and passivated on completion
From the job
6 frames · KBVI's own photographs · no stock, no renders






Send the drawings.
Get a straight answer.
One email and the pipework starts moving. Your job gets priced by the crew that welds it and stands on the site from first spool to final test.